Indicator on Program Roadmap for Teams Involved
under review
Jan Kuntscher
under review
Jan Kuntscher
Hi Russ, can you tell me why they need to see this in the roadmap view, which is designed for Product Management? Are they not using the breakout view?
R
Russell Smith
Jan Kuntscher: The Breakout view only covers the current PI, and with the Roadmap, it gives them additional PIs they can view. They would like to have this so they can do some forecasting / advanced planning of where there may be potential team load issues so they can adjust before the future PIs start. They would only be looking at this type of projection for up to 4 PIs (one year). Particularly once the Feature Points enhancement (if that is still planned) comes out, the combination would be very useful for planning.